ABOUT THE PROJECT

Mysore – Kushalnagara
Highway Development

Mysore Kushalnagara Highways Pvt Ltd is responsible for the development of the access-controlled four-lane highway project on National Highway 275 (NH-275) connecting Mysuru and Kushalnagara. The project plays a crucial role in improving transportation infrastructure and strengthening connectivity between Mysuru and the Kodagu region.

Developed under the Bharatmala Pariyojana initiative, the project aims to enhance road safety, reduce travel time, and support economic development across Karnataka. With modern engineering practices and efficient project execution, the highway is designed to provide safer, faster, and more reliable travel for commuters and transport networks.

The project corridor incorporates a combination of existing alignment improvements and strategically designed greenfield bypass sections, particularly around congested town areas such as Kushalnagara and Periyapatna. These enhancements are intended to streamline traffic movement and ensure uninterrupted highway flow.

In addition to improving connectivity, the project is expected to significantly contribute to regional development by facilitating smoother movement of goods, boosting tourism, and supporting local economies across Karnataka.

22.7 Km

Total Project Length

4 Lane

Highway Development

HAM Model

Execution Mode

NH-275

National Highway

PROJECT DETAILS

Detailed Project Information

Project Name Construction of access controlled four laning with paved shoulder from Mysore to Kushalnagara section of NH-275 (Package-II)
Highway National Highway 275 (NH-275)
Project Stretch Km 122+200 to Km 144+900 (Guddehosur to Hemming Village / SH-21 Junction)
Mode of Execution Hybrid Annuity Mode (HAM)
Configuration Four Lane Highway with Paved Shoulder
Total Length 22.700 Km
Authority National Highways Authority of India (NHAI)
Concessionaire Mysore Kushalnagara Highways Pvt Ltd
EPC Contractor D.Y. Uppar & Sons
Tender Cost ₹ 617.14 Crores
Awarded Cost ₹ 585.84 Crores
Bid Submission Date 16 February 2023
LOA Date 10 March 2023
Agreement Date 19 July 2023
Appointed Date 08 December 2025
Construction Period 24 Months (Completion: December 2027)
Concession Period 15 Years from COD