The project is being executed in structured phases to ensure timely delivery, quality construction, and compliance with national highway standards.
Execution follows defined milestones under the concession agreement ensuring systematic progress.
Payments are linked to construction progress ensuring financial discipline and transparency.
Utility shifting works are coordinated with authorities to avoid delays and disruptions.
Monthly reports are maintained to track and evaluate construction performance.
Current progress across major construction activities of the project.
| Activity | Description | Status | Progress |
|---|---|---|---|
| Project Milestones | Execution based on concession agreement milestones | On Track | 70% |
| Payment Milestones | Progress-linked payments aligned with construction stages | On Track | 65% |
| Utility Shifting | Coordination with authorities for relocation of utilities | In Progress | 60% |
| Earthwork & Excavation | Initial groundwork and land preparation activities | On Track | 75% |
| Pavement Work | Construction of road surface layers | Ongoing | 55% |
| Drainage Work | Installation of drainage systems along the highway | Ongoing | 60% |
| Structures (Bridges & Culverts) | Construction of bridges and culverts | In Progress | 50% |
| Safety & Finishing Works | Road signage, markings, barriers and safety systems | Pending | 40% |
| Monthly Progress Reports | Documentation and reporting of construction progress | Updated | 100% |